Syrah to start in Q1 2017
Hey! Looks like you have stumbled on the section of our website where we have archived articles from our old business model.
In 2019 the original founding team returned to run Next Investors, we changed our business model to only write about stocks we carefully research and are invested in for the long term.
The below articles were written under our previous business model. We have kept these articles online here for your reference.
Our new mission is to build a high performing ASX micro cap investment portfolio and share our research, analysis and investment strategy with our readers.
Click Here to View Latest Articles
Syrah Resources (ASX:SYR) has confirmed it will start production at its flagship Balama graphite project in the first quarter of 2017 – in the process becoming the largest single producer of graphite in the world.
It had previously advised the market that production at the project would begin ramp up 18 months after it had completed financing.
This month it completed a $211 million capital raising, meaning that the project is due to ramp up ahead of schedule.
The processing plant is being designed to have a feed rate of 2 million tonnes of graphite ore per year with an average grade of 19% total graphitic carbon, meaning it has a nameplate processing capability of 356,000 tonnes of total graphitic carbon of over 95%.
SYR said this will make the Balama Project the single biggest producer of graphite in the world, right when demand for lithium ion batteries is scheduled to ramp up.
Last week Toronto Stock Exchange-listed Pure Energy Minerals announced that it had tied up a supply deal with Tesla Motors for the supply of lithium hydroxide from its Nevada brine project – a deal which some read as a possible preview of the sorts of deals manufacturers could seek to do with miners.
SYR said it was quietly ticking the boxes on the project ahead of ramp up, with it starting to identify the sort of long-lead items it will need on the project ahead of placing orders in the coming months.
It is also conducted detailed engineering on the processing plant, and is currently testing the marketing waters.
At the end of May SYR announced that it had wrapped up a feasibility study into the project, finding that its processing plant would have an effective life of 42 years with a payback on capital period of less than two years.
General Information Only
S3 Consortium Pty Ltd (S3, ‘we’, ‘us’, ‘our’) (CAR No. 433913) is a corporate authorised representative of LeMessurier Securities Pty Ltd (AFSL No. 296877). The information contained in this article is general information and is for informational purposes only. Any advice is general advice only. Any advice contained in this article does not constitute personal advice and S3 has not taken into consideration your personal objectives, financial situation or needs. Please seek your own independent professional advice before making any financial investment decision. Those persons acting upon information contained in this article do so entirely at their own risk.
Conflicts of Interest Notice
S3 and its associated entities may hold investments in companies featured in its articles, including through being paid in the securities of the companies we provide commentary on. We disclose the securities held in relation to a particular company that we provide commentary on. Refer to our Disclosure Policy for information on our self-imposed trading blackouts, hold conditions and de-risking (sell conditions) which seek to mitigate against any potential conflicts of interest.
Publication Notice and Disclaimer
The information contained in this article is current as at the publication date. At the time of publishing, the information contained in this article is based on sources which are available in the public domain that we consider to be reliable, and our own analysis of those sources. The views of the author may not reflect the views of the AFSL holder. Any decision by you to purchase securities in the companies featured in this article should be done so after you have sought your own independent professional advice regarding this information and made your own inquiries as to the validity of any information in this article.
Any forward-looking statements contained in this article are not guarantees or predictions of future performance, and involve known and unknown risks, uncertainties and other factors, many of which are beyond our control, and which may cause actual results or performance of companies featured to differ materially from those expressed in the statements contained in this article. S3 cannot and does not give any assurance that the results or performance expressed or implied by any forward-looking statements contained in this article will actually occur and readers are cautioned not to put undue reliance on forward-looking statements.
This article may include references to our past investing performance. Past performance is not a reliable indicator of our future investing performance.